Coordination for FACADE Work

The following are the main important points to be prepared and Hand over to FACADE subcontractors:


  • As Built survey for slab edge - All floor.
  •  Levels every floor.
  • Survey control points.
  • verification of Levels and location of embedded Facede brackets
  • storage location for Facade panels.
  • offices and tools  storage -  As per contract.
  • Life line rope - As per contract
  • Cradles - As per contract.
  • Erection of Scaffolding-As per contract.
FACADE  subcontractor have to submit the followings;
  • Method of statement.
  • Panels delivery schedules.
  • Direct and indirect Manpower.
  • All documents related to MIR during materials delivery.
  • Pull test report by 3rd. party.
And during construction:
  • Mock up to be prepared for each type of Facade or as per contract.
  • Pressure test by 3rd. party to be passed.
  
More site support to be given to FACADE subcontractor to push his progress and this means IPC amount will be increased.


to be continued ....... 